Long term maintenance optimization of CCGT plants

E. Lobato, P. Sánchez, E. Saiz

4th IEEE PES Asia-Pacific Power and Energy Engineering Conference - APPEEC 2012, Shanghai (China). 27-29 March 2012


Summary:

The rising share of renewable energies within the generation mix has reduced the load factor of actual CCGT power plants. In this way, a more flexible operation of this technology with an increased number of annual start-up cycles is needed. Since CCGT design assumed a base load operation at nominal power with a few number of annual start cycles, plant owners have to face higher maintenance costs, reliability reduction and lower market incomes. This paper presents a mixed-integer optimization model that schedules the long term maintenance planning based on the daily operation of a CCGT plant in order to maximize its global profit. The model is illustrated with an actual CCGT plant operating in the Spanish power system.


Keywords: maintenance planning; unitcommitment; optimization models


DOI: DOI icon https://doi.org/10.1109/APPEEC.2012.6307471

Published in APPEEC 2012, pp: 1-4, ISBN: 978-1-4577-0545-8

Publication date: 2012-09-20.



Citation:
E. Lobato, P. Sánchez, E. Saiz, Long term maintenance optimization of CCGT plants, 4th IEEE PES Asia-Pacific Power and Energy Engineering Conference - APPEEC 2012, Shanghai (China). 27-29 March 2012. In: APPEEC 2012: Conference proceedings, ISBN: 978-1-4577-0545-8